Build from resolved details.
This guide follows the uploaded 3508 Hanover revised plan set 9_2026. Drawing facts are cited by sheet. The work sequence, trade assignments and checklists are planning guidance. The uploaded set’s permit status and the complete approved shop drawings have not been verified.
Decisions to close before the affected work
- Construction release: confirm the approved revision, governing code edition, complete geotechnical documents and the S6.4 reference in the cover index.
- Earthwork: resolve S1’s 30-in fill requirement and 93% ASTM D1557 compaction against the civil section’s 90% language. Establish one approved instruction for each fill area.
- Drilling: verify actual bearing/rock embedment, bore stability, water conditions and any change to scheduled shaft depths.
- Slab reinforcement: resolve S1’s generic fiber / #3 at 18-in note against S3’s #3 at 12-in schedule.
- Retaining wall: obtain the existing-wall connection after exposure; confirm wall tops, drainage outlet, water protection, non-expansive backfill and loading release.
- Structural panels: approve actual ThermaSteel shop drawings, member/connection details, service penetrations, lifting, bracing, shoring and construction loading.
- Floor finish: A2 calls for stained concrete; A4 F1 calls for wood-look LVP. Resolve finish and thickness before thresholds, drains and cabinetry are fixed.
- Water heater: P1 calls for 50 gallons while T24.2/T24.3 model 80 gallons. Coordinate the actual heat-pump product, location, efficiency and service requirements.
- Energy and solar: coordinate installed envelope values, equipment, ventilation and required verification. T24.4’s modeled equivalent assemblies do not replace structural details; the modeled 2.64-kW PV value is not a shop drawing.
- Enclosure and fire protection: approve roof slope/product compatibility, opening ratings, WUI/rated assemblies and the deferred sprinkler design before related procurement or concealment.
What the visuals show
The 3D model shows the overall building and its major construction layers. Detail diagrams explain assembly relationships; they are not fabrication drawings. Several work steps share the same major model layer. Small components, fasteners and service routes are not an exact fabrication model. Use the approved civil, structural, architectural and manufacturer documents for dimensions, reinforcement, fastening, lifting, bracing and curing requirements. Furniture and finish appearances are illustrative. Selecting a step records no construction completion or inspection approval.
Inspection and reference resources
Confirm Hanover’s inspection card and required hold points with the assigned inspector. City resources checked September 19, 2026:
- Santa Rosa building forms and inspection-code handout — current forms, special-inspection documents and scheduling reference.
- Residential building permit checklist — document coordination and deferred sprinkler requirements.
- Fire construction plan review and inspections — sprinkler plan review and Fire inspection coordination.
Drawing guide: PD (PDF p. 1); civil G1–G3 (pp. 2–4); L1 (p. 5); A1–A4 (pp. 6–9); M1/E1/P1/P1.1/EN1 (pp. 10–14); CALGreen and energy documents (pp. 15–19); S1–S4.1 (pp. 20–24); S5–S8.3 (pp. 25–34).